Dept. of Trans. PROGRESS Serial No. Contract No. 20-262-15-00 03-3H4004 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 39% Location: Federal Project: 03-SIE-49-44.1/44.4 HSST-S049(181) Progress payment No. 002 Payment period ending: 09-20-20 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 521,452.52 416,162.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 521,452.52 416,162.50 5. Mobilization 215,650.00 102,150.00 6. Total Work Completed 737,102.52 7. Deductions -42,983.80 -20,360.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 694,118.72 497,951.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 497,951.75