Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-359-13-12 03-3H4004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SIE-49-44.1/44.4 HSST-S049(181) Progress payment No. 005 Payment period ending: 12-01-20 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,586,644.95 52,321.72 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,586,644.95 52,321.72 5. Mobilization 227,000.00 0.00 6. Total Work Completed 1,813,644.95 7. Deductions -40,936.31 16,309.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,772,708.64 68,631.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,631.52