Dept. of Trans. PROGRESS Serial No. Contract No. 20-267-09-05 03-3H4504 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 2% Location: Federal Project: 03-ED-50-33.8/34.2 NONE Progress payment No. 001 Payment period ending: 09-20-20 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 161,731.68 161,731.68 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 209,275.51 209,275.51 4. Earned Subject to Retention 371,007.19 371,007.19 5. Mobilization 6. Total Work Completed 161,731.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 371,007.19 371,007.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 371,007.19