Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-275-12-50 03-3H4504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-50-33.8/34.2 NONE Progress payment No. 034 Payment period ending: 08-18-23 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,185,073.86 -104,152.46 2. a. Extra Work 131,417.64 0.00 b. Adustment Comp. 51,287.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,367,779.16 -104,152.46 5. Mobilization 1,050,000.00 0.00 6. Total Work Completed 11,417,779.16 7. Deductions -2,005,000.00 -660,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,412,779.16 -764,152.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -764,152.46