Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-10-12 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 0% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 002 Payment period ending: 06-20-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,127,159.95 487,661.25 2. a. Extra Work 7,982.34 7,982.34 b. Adustment Comp. -41,000.00 -41,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,094,142.29 454,643.59 5. Mobilization 1,340,000.00 1,340,000.00 6. Total Work Completed 2,434,142.29 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,431,142.29 1,794,643.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,794,643.59