Dept. of Trans. PROGRESS Serial No. Contract No. 23-257-13-01 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 18% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 006 Payment period ending: 09-20-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,633,474.35 1,515,579.61 2. a. Extra Work 25,473.44 0.00 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 963,096.00 211,613.74 4. Earned Subject to Retention 6,581,043.79 1,727,193.35 5. Mobilization 2,546,000.00 536,000.00 6. Total Work Completed 8,163,947.79 7. Deductions -17,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,110,043.79 2,263,193.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,263,193.35