Dept. of Trans. PROGRESS Serial No. Contract No. 23-355-13-37 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 36% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 009 Payment period ending: 12-20-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,533,217.26 1,780,446.46 2. a. Extra Work 58,647.22 17,630.14 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 425,544.00 293,142.00 4. Earned Subject to Retention 9,976,408.48 2,091,218.60 5. Mobilization 2,546,000.00 0.00 6. Total Work Completed 12,096,864.48 7. Deductions 0.00 9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,522,408.48 2,100,218.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,100,218.60