Dept. of Trans. PROGRESS Serial No. Contract No. 24-019-10-14 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 42% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 010 Payment period ending: 01-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,573,574.13 1,040,356.88 2. a. Extra Work 132,644.43 73,997.21 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 1,132,619.00 707,075.00 4. Earned Subject to Retention 11,797,837.56 1,821,429.09 5. Mobilization 2,546,000.00 0.00 6. Total Work Completed 13,211,218.56 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,339,837.56 1,817,429.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,817,429.09