Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-11-33 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 43% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 011 Payment period ending: 02-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,222,140.21 648,566.08 2. a. Extra Work 144,232.61 11,588.18 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 504,853.00 -627,766.00 4. Earned Subject to Retention 11,830,225.82 32,388.26 5. Mobilization 2,546,000.00 0.00 6. Total Work Completed 13,871,372.82 7. Deductions -6,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,370,225.82 30,388.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,388.26