Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-13-41 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 43% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 013 Payment period ending: 04-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,147,304.60 717,953.05 2. a. Extra Work 870,887.45 239,636.04 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 1,246,741.00 1,112,832.00 4. Earned Subject to Retention 14,223,933.05 2,070,421.09 5. Mobilization 2,680,000.00 134,000.00 6. Total Work Completed 15,657,192.05 7. Deductions -7,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,896,933.05 2,203,421.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,203,421.09