Dept. of Trans. PROGRESS Serial No. Contract No. 24-141-08-15 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 45% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 014 Payment period ending: 05-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,556,219.64 1,408,915.05 2. a. Extra Work 1,282,268.50 411,381.05 b. Adustment Comp. -41,000.00 0.00 3. Materials on Hand 504,853.00 -741,888.00 4. Earned Subject to Retention 15,302,341.14 1,078,408.10 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 17,477,488.14 7. Deductions -10,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,972,341.14 1,075,408.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,075,408.10