Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-13-54 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 43% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 017 Payment period ending: 08-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,910,820.10 1,103,295.66 2. a. Extra Work 2,300,358.83 350,527.17 b. Adustment Comp. -459,955.81 0.00 3. Materials on Hand 845,526.00 -58,308.00 4. Earned Subject to Retention 20,596,749.12 1,395,514.83 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 22,431,223.12 7. Deductions -14,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,262,749.12 1,393,514.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,393,514.83