Dept. of Trans. PROGRESS Serial No. Contract No. 24-263-08-19 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 72% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 018 Payment period ending: 09-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,522,254.35 1,611,434.25 2. a. Extra Work 2,305,083.83 4,725.00 b. Adustment Comp. -459,955.81 0.00 3. Materials on Hand 936,763.00 91,237.00 4. Earned Subject to Retention 22,304,145.37 1,707,396.25 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 24,047,382.37 7. Deductions -12,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,972,145.37 1,709,396.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,709,396.25