Dept. of Trans. PROGRESS Serial No. Contract No. 24-323-14-04 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 84% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 020 Payment period ending: 11-20-24 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,971,464.60 1,210,191.05 2. a. Extra Work 3,222,330.26 887,988.30 b. Adustment Comp. -459,955.81 0.00 3. Materials on Hand 712,908.00 -129,149.00 4. Earned Subject to Retention 25,446,747.05 1,969,030.35 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 27,413,839.05 7. Deductions -2,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,124,747.05 1,979,030.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,979,030.35