Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-14-59 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 22% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 022 Payment period ending: 01-20-25 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,628,082.60 284,698.00 2. a. Extra Work 3,499,881.89 104,922.46 b. Adustment Comp. -459,955.81 0.00 3. Materials on Hand 607,866.00 -184,489.00 4. Earned Subject to Retention 26,275,874.68 205,131.46 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 28,348,008.68 7. Deductions -16,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,939,874.68 195,131.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 195,131.46