Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-09-48 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 83% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 023 Payment period ending: 02-20-25 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,628,642.60 560.00 2. a. Extra Work 3,499,881.89 0.00 b. Adustment Comp. -459,955.81 0.00 3. Materials on Hand 607,866.00 0.00 4. Earned Subject to Retention 26,276,434.68 560.00 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 28,348,568.68 7. Deductions -2,000.00 14,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,954,434.68 14,560.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,560.00