Dept. of Trans. PROGRESS Serial No. Contract No. 25-083-13-49 03-3H5404 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 83% Location: Federal Project: 03-BUT-70-46.0/47.0 ACST-ER(31P) Progress payment No. 024 Payment period ending: 03-20-25 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,729,702.60 1,101,060.00 2. a. Extra Work 3,668,435.45 168,553.56 b. Adustment Comp. -456,827.97 3,127.84 3. Materials on Hand 0.00 -607,866.00 4. Earned Subject to Retention 26,941,310.08 664,875.40 5. Mobilization 2,680,000.00 0.00 6. Total Work Completed 29,621,310.08 7. Deductions -1,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,620,310.08 665,875.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 665,875.40