Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-10-41 03-3H5604 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 15% Location: Federal Project: 03-VAR BFNH-000C(560) Progress payment No. 007 Payment period ending: 12-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,699,534.98 38,277.00 2. a. Extra Work 89,300.05 73,735.52 b. Adustment Comp. -3,000.00 -3,000.00 3. Materials on Hand 162,691.00 124,827.00 4. Earned Subject to Retention 9,948,526.03 233,839.52 5. Mobilization 6,224,250.00 0.00 6. Total Work Completed 16,010,085.03 7. Deductions -4,090.96 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,168,685.07 231,839.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,839.52