Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-07-53 03-3H5604 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 15% Location: Federal Project: 03-VAR BFNH-000C(560) Progress payment No. 010 Payment period ending: 03-20-25 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,916,802.73 3,558.50 2. a. Extra Work 1,405,122.44 666,708.82 b. Adustment Comp. -3,000.00 0.00 3. Materials on Hand 162,691.35 0.00 4. Earned Subject to Retention 11,481,616.52 670,267.32 5. Mobilization 6,224,250.00 0.00 6. Total Work Completed 17,543,175.17 7. Deductions -90.96 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,705,775.56 670,267.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 670,267.32