Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-08-10 03-3H5604 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 17% Location: Federal Project: 03-VAR BFNH-000C(560) Progress payment No. 011 Payment period ending: 04-20-25 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,921,806.90 1,005,004.17 2. a. Extra Work 1,835,246.97 430,124.53 b. Adustment Comp. -3,000.00 0.00 3. Materials on Hand 162,691.35 0.00 4. Earned Subject to Retention 12,916,745.22 1,435,128.70 5. Mobilization 6,224,250.00 0.00 6. Total Work Completed 18,978,303.87 7. Deductions -359,623.13 -359,532.17 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,781,372.09 1,075,596.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,075,596.53