Dept. of Trans. PROGRESS Serial No. Contract No. 26-082-10-11 03-3H6104 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 100% Location: Federal Project: 03-PLA-80-42.7/49.3 ACIM-804(336) Progress payment No. 023 Payment period ending: 03-20-26 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,116,245.77 -114,533.58 2. a. Extra Work 8,948,584.96 852,299.58 b. Adustment Comp. 1,339,658.04 0.00 3. Materials on Hand 2,107,325.08 0.00 4. Earned Subject to Retention 69,511,813.85 737,766.00 5. Mobilization 12,100,000.00 0.00 6. Total Work Completed 79,504,488.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 81,611,813.85 737,766.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 737,766.00