Dept. of Trans. PROGRESS Serial No. Contract No. 21-265-16-52 03-3H72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 26% Location: Federal Project: 03-BUT-70-5.6/9.1 ACNH-P070(141) Progress payment No. 012 Payment period ending: 09-20-21 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,782,216.93 1,718,744.55 2. a. Extra Work 280,617.47 46,966.03 b. Adustment Comp. 154,637.48 -2,282.73 3. Materials on Hand 4. Earned Subject to Retention 10,217,471.88 1,763,427.85 5. Mobilization 627,000.00 0.00 6. Total Work Completed 10,844,471.88 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,834,471.88 1,763,427.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,763,427.85