Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-07-32 03-3H72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 33% Location: Federal Project: 03-BUT-70-5.6/9.1 ACNH-P070(141) Progress payment No. 025 Payment period ending: 06-20-23 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,564,470.71 0.00 2. a. Extra Work 1,629,772.47 103,402.18 b. Adustment Comp. 816,076.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,010,319.90 103,402.18 5. Mobilization 627,000.00 0.00 6. Total Work Completed 15,637,319.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,637,319.90 103,402.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,402.18