Dept. of Trans. PROGRESS Serial No. Contract No. 18-039-14-37 03-3H8104 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 78% Location: Federal Project: 03-VAR NONE Progress payment No. 002 Payment period ending: 02-06-18 GRANITE CONSTRUCTION COMPANY 1900 GLENDALE AVE SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 347,487.21 48,660.93 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 347,487.21 48,660.93 5. Mobilization 6. Total Work Completed 347,487.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 347,487.21 48,660.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,660.93