Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-14-14 03-3H9014 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 22% Location: Federal Project: 03-VAR NFRA-6203(70) Progress payment No. 004 Payment period ending: 07-20-25 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,161,120.54 2,243,821.40 2. a. Extra Work 38,173.18 38,173.18 b. Adustment Comp. 15,661.00 21,840.00 3. Materials on Hand 134,932.22 134,932.22 4. Earned Subject to Retention 10,349,886.94 2,438,766.80 5. Mobilization 6,200,000.00 0.00 6. Total Work Completed 16,414,954.72 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,547,886.94 2,436,766.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,436,766.80