Dept. of Trans. PROGRESS Serial No. Contract No. 26-147-11-42 03-3J3604 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 65% Location: Federal Project: 03-NEV-89-R5.3/8.7 NONE 03-SIE-89-0.0/29.6 Progress payment No. 011 Payment period ending: 05-20-26 TEICHERT ENERGY & UTILITIES GROUP INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,941,026.37 3,871,417.88 2. a. Extra Work 253,924.89 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 19,194,951.26 3,871,417.88 5. Mobilization 3,371,917.09 168,595.85 6. Total Work Completed 22,566,868.35 7. Deductions -2,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,564,868.35 4,041,013.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,041,013.73