Dept. of Trans. PROGRESS Serial No. Contract No. 26-169-08-40 03-3J40U4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 47% Location: Federal Project: 03-VAR NONE Progress payment No. 010 Payment period ending: 06-20-26 TEICHERT ENERGY & UTILITIES GROUP INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,264,390.94 2,712,210.83 2. a. Extra Work 60,675.21 9,856.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 17,325,066.15 2,722,067.58 5. Mobilization 4,912,211.05 0.00 6. Total Work Completed 22,237,277.20 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,234,277.20 2,722,067.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,722,067.58