Dept. of Trans. PROGRESS Serial No. Contract No. 26-232-14-05 03-3J40U4 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 57% Location: Federal Project: 03-VAR NONE Progress payment No. 012 Payment period ending: 08-20-26 TEICHERT ENERGY & UTILITIES GROUP INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,035,062.85 3,738,786.62 2. a. Extra Work 314,647.46 253,972.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 26,349,710.31 3,992,758.87 5. Mobilization 5,170,748.47 258,537.42 6. Total Work Completed 31,520,458.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,520,458.78 4,251,296.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,251,296.29