Dept. of Trans. PROGRESS Serial No. Contract No. 25-171-08-28 03-3J7504 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 100% Location: Federal Project: 03-PLA-49-4.6/4.9 NONE Progress payment No. 004 Payment period ending: 06-20-25 DOUG VEERKAMP GENERAL ENGINEERING INC. 3701 TRADE WAY CAMERON PARK CA 95682 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 736,348.18 320,377.80 2. a. Extra Work 8,750.00 8,750.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 745,098.18 329,127.80 5. Mobilization 6. Total Work Completed 745,098.18 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 745,098.18 330,127.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 330,127.80