Dept. of Trans. PROGRESS Serial No. Contract No. 09-167-10-38 03-3M0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 58% 03-GLE-162-R45.1/65.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-19-09 FRANKLIN CONSTRUCTION INC P O BOX 3100 CHICO CA 95927 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 997,985.96 727,195.07 2.a. Extra Work b. Adjustment Comp. -1,373.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 996,612.81 727,195.07 5. Mobilization 6. Total Work Completed 996,612.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 996,612.81 727,195.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 727,195.07