Dept. of Trans. PROGRESS Serial No. Contract No. 11-021-10-00 03-3M2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 35% 03-PLA-65-R4.8/R8.7 Federal Project: NONE Progress payment No. 05 Payment period ending: 01-20-11 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP CA 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 427,130.45 162,270.00 2.a. Extra Work 5,232.55 5,232.55 b. Adjustment Comp. 3. Materials on Hand 90,645.00 45,322.50 4. Earned Subject to Retention 523,008.00 212,825.05 5. Mobilization 15,000.00 0.00 6. Total Work Completed 447,363.00 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 536,008.00 212,825.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 212,825.05