Dept. of Trans. PROGRESS Serial No. Contract No. 10-203-14-35 03-3M3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 85% 03-PLA-80-7.4/R66.3 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-20-10 T AND G CONSTRUCTION INC 598 GARDEN HIGHWAY, SUITE 2 YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 181,439.95 41,281.55 2.a. Extra Work 21,500.00 21,500.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 202,939.95 62,781.55 5. Mobilization 20,000.00 0.00 6. Total Work Completed 222,939.95 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 221,939.95 61,781.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,781.55