Dept. of Trans. FINAL Serial No. Contract No. 10-363-15-23 03-3M3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-7.4/R66.3 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-03-10 T AND G CONSTRUCTION INC 598 GARDEN HIGHWAY, SUITE 2 YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 182,606.55 0.00 2.a. Extra Work 24,079.66 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 206,686.21 0.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 226,686.21 7. Deductions 0.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 226,686.21 1,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000.00