Dept. of Trans. PROGRESS Serial No. Contract No. 10-265-08-07 03-3M3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 98% 03-YUB-65-R7.4/R9.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-16-10 PROFESSIONAL CONSTRUCTION SERVICES 4070 NELSON AVENUE SUITE A CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 441,284.67 148,850.18 2.a. Extra Work 56,550.59 56,550.59 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 497,835.26 205,400.77 5. Mobilization 8,500.00 0.00 6. Total Work Completed 506,335.26 7. Deductions -7,000.00 53,124.12 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 499,335.26 258,524.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,524.89