Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-16-51 03-3M4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 90% 03-ED-50-45.2/45.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-10 B AND B DEVELOPERS 4804 LAUREL CANYON BLVD NO 24 VALLEY VILLAGE CA 91607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 133,863.90 113,839.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 133,863.90 113,839.30 5. Mobilization 6. Total Work Completed 133,863.90 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 123,863.90 103,839.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,839.30