Dept. of Trans. PROGRESS Serial No. Contract No. 09-232-13-26 03-3M4804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 49% 03-YOL-113-22.0/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-20-09 JEFFCO PAINTING AND COATING INC P O BOX 1888 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 505,975.26 139,107.79 2.a. Extra Work 392.70 392.70 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 506,367.96 139,500.49 5. Mobilization 48,195.00 2,409.75 6. Total Work Completed 554,562.96 7. Deductions -10,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 544,562.96 137,910.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 137,910.24