Dept. of Trans. PROGRESS Serial No. Contract No. 11-231-14-36 03-3M6704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 58% 03-NEV-89-0.4/4.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-19-11 Q AND D CONSTRUCTION CO 1050 SOUTH 21ST STREET SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 112,613.00 112,613.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 112,613.00 112,613.00 5. Mobilization 31,350.00 31,350.00 6. Total Work Completed 143,963.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 143,963.00 143,963.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,963.00