Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-11-53 03-3M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 87% 03-SAC-160-5.9/21.1 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-19-12 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,568,977.06 133,563.24 2.a. Extra Work 39,048.27 19,624.18 b. Adjustment Comp. -65,061.14 -65,061.14 3. Materials on Hand 4. Earned Subject to Retention 5,542,964.19 88,126.28 5. Mobilization 697,760.00 0.00 6. Total Work Completed 6,240,724.19 7. Deductions -62,154.40 -19,390.81 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,178,569.79 68,735.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,735.47