Dept. of Trans. PROGRESS Serial No. Contract No. 12-234-14-32 03-3M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 96% 03-SAC-160-5.9/21.1 Federal Project: NONE Progress payment No. 12 Payment period ending: 08-20-12 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,731,684.45 162,707.39 2.a. Extra Work 39,048.27 0.00 b. Adjustment Comp. -65,061.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,705,671.58 162,707.39 5. Mobilization 697,760.00 0.00 6. Total Work Completed 6,403,431.58 7. Deductions -79,440.43 -17,286.03 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,323,991.15 145,421.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,421.36