Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-276-09-16 03-3M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-160-5.9/21.1 Federal Project: NONE Progress payment No. 13 Payment period ending: 09-05-12 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,083,512.64 351,828.19 2.a. Extra Work 40,059.28 1,011.01 b. Adjustment Comp. -65,061.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,058,510.78 352,839.20 5. Mobilization 697,760.00 0.00 6. Total Work Completed 6,756,270.78 7. Deductions -56,473.23 22,967.20 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,699,797.55 375,806.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 375,806.40