Dept. of Trans. FINAL Serial No. Contract No. 14-122-07-54 03-3M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-160-5.9/21.1 Federal Project: NONE Progress payment No. 17 Payment period ending: 09-05-12 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,099,768.32 0.00 2.a. Extra Work 118,642.06 0.00 b. Adjustment Comp. -62,993.01 4,568.13 3. Materials on Hand 4. Earned Subject to Retention 6,155,417.37 4,568.13 5. Mobilization 697,760.00 0.00 6. Total Work Completed 6,853,177.37 7. Deductions -36,473.23 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,816,704.14 4,568.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,568.13