Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-11-28 03-3M7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 37% 03-SAC-80-3.6/16.7 Federal Project: NONE Progress payment No. 07 Payment period ending: 05-17-12 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 451,306.43 74,950.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,306.43 74,950.00 5. Mobilization 65,000.00 0.00 6. Total Work Completed 516,306.43 7. Deductions 0.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 516,306.43 75,950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,950.00