Dept. of Trans. PROGRESS Serial No. Contract No. 11-353-13-19 03-3M8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 62% 03-NEV-80-13.5/21.2 Federal Project: ACIM-804(196) Progress payment No. 06 Payment period ending: 12-19-11 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,096,985.71 53,750.00 2.a. Extra Work 7,679.45 7,679.45 b. Adjustment Comp. -53,149.57 -53,149.57 3. Materials on Hand 4. Earned Subject to Retention 4,051,515.59 8,279.88 5. Mobilization 6. Total Work Completed 4,051,515.59 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,048,515.59 5,279.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,279.88