Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-11-37 03-3M8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 62% 03-NEV-80-13.5/21.2 Federal Project: ACIM-804(196) Progress payment No. 10 Payment period ending: 05-17-12 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,629,011.20 532,025.49 2.a. Extra Work 19,324.71 0.00 b. Adjustment Comp. -53,149.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,595,186.34 532,025.49 5. Mobilization 6. Total Work Completed 4,595,186.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,595,186.34 532,025.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 532,025.49