Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-09-52 03-3M8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 86% 03-NEV-80-13.5/21.2 Federal Project: ACIM-804(196) Progress payment No. 14 Payment period ending: 09-17-12 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,769,309.55 0.00 2.a. Extra Work 339,784.72 140,500.00 b. Adjustment Comp. -53,149.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,055,944.70 140,500.00 5. Mobilization 6. Total Work Completed 7,055,944.70 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,050,944.70 140,500.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,500.00