Dept. of Trans. PROGRESS Serial No. Contract No. 11-172-10-36 03-3M9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 26% 03-ED-49-11.9/15.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-16-11 TEICHERT CONSTRUCTION P O BOX 700 LINCOLN CA 95648 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 361,303.75 359,966.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 361,303.75 359,966.25 5. Mobilization 6. Total Work Completed 361,303.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 361,303.75 359,966.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,966.25