Dept. of Trans. PROGRESS Serial No. Contract No. 11-294-11-48 03-3M9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 97% 03-PLA-267-0.0/3.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-11 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 868,143.07 65,584.16 2.a. Extra Work b. Adjustment Comp. -26,385.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 841,757.65 65,584.16 5. Mobilization 6. Total Work Completed 841,757.65 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -6,558.42 -6,558.42 c. Reduction after 95% Comp. 9. Total pay to Contractor 833,199.23 57,025.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,025.74