Dept. of Trans. PROGRESS Serial No. Contract No. 07-172-12-01 03-401804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 18% 03-YUB-65-0.5/1.5 Federal Project: ACST-P065(86) P-P065(86) Progress payment No. 02 Payment period ending: 06-15-07 BALDWIN CONTRACTING COMPANY INC 4509 SKYWAY DRIVE MARYSVILLE CA 95901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 159,180.25 127,789.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -22,375.78 4. Earned Subject to Retention 159,180.25 105,413.51 5. Mobilization 27,500.00 27,500.00 6. Total Work Completed 186,680.25 7. Deductions -7,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 179,680.25 127,913.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 127,913.51