Dept. of Trans. PROGRESS Serial No. Contract No. 04-147-07-38 03-402304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 45% 03-GLE-32-R4.8/5.9 Federal Project: ACST-P032(34) P-P032(34) Progress payment No. 14 Payment period ending: 05-20-04 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 02023 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,934,234.76 85,064.00 2.a. Extra Work 232,809.01 2,357.94 b. Adjustment Comp. 36,102.40 0.00 3. Materials on Hand 71,761.97 -71,761.97 4. Earned Subject to Retention 4,274,908.14 15,659.97 5. Mobilization 878,009.00 0.00 6. Total Work Completed 5,081,155.17 7. Deductions -14,374.21 0.00 8. a.Contract Retentions -213,745.41 -783.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,924,797.52 14,876.97 10. Reduction Amt to Escrow 11. Payment to Escrow 213,740.00 12. Net Pymt. this Estimate 14,876.97