Dept. of Trans. PROGRESS Serial No. Contract No. 14-300-09-30 03-406604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 41% 03-SUT-99-0.0/1.6 Federal Project: HP21-L620(304) Progress payment No. 19 Payment period ending: 10-20-14 TEICHERT CONSTRUCTION 4401 DULUTH AVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,393,362.60 1,299,193.94 2.a. Extra Work 227,008.70 8,223.80 b. Adjustment Comp. 311,084.08 144,229.44 3. Materials on Hand 4. Earned Subject to Retention 15,931,455.38 1,451,647.18 5. Mobilization 1,231,600.00 0.00 6. Total Work Completed 17,163,055.38 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,163,055.38 1,456,647.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,456,647.18